RATE SCHEDULE T-1
FIRM SERVICE
5. RIGHT OF FIRST REFUSAL (Continued)
5.2 Posting/Bid Procedures (Continued)
5.22 Bid Procedures (Continued)
(c) The Company will allow Bids for capacity which
are contingent upon the bidder obtaining capacity
on another pipeline(s). The Bid must specify the
contingency, including the timing of when the
results of the other pipeline(s) evaluation and
allocation process will be completed. In those
instances where such a contingent Bid(s) is
determined to be the Best Bid, the allocation of
capacity may be delayed, without undue
discrimination, pending satisfaction of the
contingency. If such contingency has not been
resolved by no later than 10 business days after
Bid Closing Date, then such contingent bid is
deemed void.
(d) If a Bid is received which contains conditions,
other than those allowed in Subsection 5.22(c),
that are not satisfied at Bid Closing Date, such
Bid shall not be accepted.
(e) A bidder may withdraw its Bid prior to the Bid
Closing Date upon written notice to Company.
5.23 Selection of Best Bid
(a) For purposes of determining the Best Bid(s),
Company will use Method A as detailed in
Subsection 27.61(a) and, if applicable for
Negotiated Rate bids, Subsection 38.3 of the
General Terms and Conditions. (Where competing
Bids at less than the Maximum Rate are received,
Shipper need not match the Bid unless the less
than Maximum Rate Bid is accepted by Company.)
(b) Company will evaluate Bids received within one
business day of the Bid Closing Date except as
noted in Subsection 5.22(c).
|
Issued by: Bambi L. Heckerman, Manager, Regulatory Affairs