Previous  Next  Search 
Northern Border Pipeline Company
FERC Gas Tariff
First Revised Volume No. 1

First Revised Sheet No. 180A
Superseding
Original Sheet No. 180A

                              RATE SCHEDULE T-1B
                             FIRM BACKHAUL SERVICE


  3.  RATES (Continued)

       3.1   Rates (Continued)

                  Compressor Usage Surcharge - The Compressor Usage 
                  Surcharge is defined and computed in accordance with 
                  Section 45 of the General Terms and Conditions of 
                  Company's FERC Gas Tariff and only shall be applicable 
                  if secondary points are utilized which reverse the 
                  directional flow of Shipper's contractual firm back-
                  haul service to a forward-haul service.

       3.2   Discounted Rates

             Company shall charge the applicable Maximum Reservation 
             Rate and applicable Maximum Commodity Rate set forth on the 
             Statement of Rates applicable to service hereunder unless 
             Company, from time to time and at any time at its 
             discretion on a non-discriminatory basis, charges any 
             individual Shipper for transportation service under this 
             Rate Schedule a rate which is lower than the Maximum Rate 
             hereunder; provided, however, that the total amount charged 
             may not be less than the applicable Maximum Commodity 
             Rate(s) set forth on the currently effective Statement of 
             Rates of Company's FERC Gas Tariff, plus the effective 
             Annual Charge Adjustment and the Compressor Usage 
             Surcharge.

             In the event secondary points are utilized which impact the 
             directional flow of a discounted transaction, such discount 
             shall not be applicable to such secondary points and 
             utilization of such secondary points shall be billed the 
             applicable Maximum Commodity Rate under Rate Schedule IT-1 
             set forth on the currently effective Statement of Rates.

Issued by: Raymond D. Neppl, Vice President
Issued on: November 21, 2006                  Effective on: January 1, 2007
Filed to comply with order of the Federal Energy Regulatory Commission, Docket 
No. RP06-72-000, issued November 21, 2006, 17 FERC ¶ 61,217
 Previous  Next  Search